Methanex Chile IV
Methanex Chile IV
Completion of 2500 MTPD Methanol Plant; 2004-2005
Location: Punta Arenas, Chile
Approx. Project Value: USD $240 000 000
Services: Instrumentation and Control Systems
Responsibilities:
Review, correct, implement and fully test all ESD (SIS) Logic and DCS complex control strategies before startup of all plant units.
Advise on construction quality control, pre-commissioning, commissioning, turnover and startup activities related to instrumentation and process control.
Coordination with operating team for all instrumentation and process control activities.